Partnership delivers success for large-scale transpooling project
01 OCTOBER 2024
Motive Technicians worked together with HCS in Fife, carrying out transpooling of product from 105 reels onto storage reels for the end client.

For the uninitiated, getting product from Reel A onto Reel B may seem a simple process, but in this case a high level of engineering input was required from the outset to ensure a safe and efficient solution was in place. Consideration around output torques was especially important for handling the high-end steel to avoid any stresses on the product.
Motive supplied a full transpooling package including 75Te Spooling Winches, 5Te Tensioner, Levelwind, and a 5Te Hydraulic Drum Winch, accompanied by a team of 6 multi-disciplined Personnel.